Following proposals GM&E has prepared and submitted to different clients in 2018 till present with a total amount of more than EUR 510 million. Throw GM&E professional proposal calculation and preparation.
1- SIRTE OIL COMPANY REHABILITATION OF NAPHTHA TANK TK-14, CRUDE OIL TANK FARM, BREGA (TP-220304T).
The objective of this project is to carry out repair works to the existing Naphtha Storage Tank TK-14, 200 feet diameter x 48 feet high; capacity of 268000 barrels, Single Deck Floating Roof. Tank was designed and constructed/ erected in accordance with API 650.
The work includes Engineering (Mechanical, Instrumentation, Electrical), Procurement, Construction and Commissioning Jobs. It involves inspection, procurement of materials, removal/ replacement of damaged plates, fabrication, alignment, welding, testing, cleaning, and surface preparation.
2- SIRTE OIL COMPANY MAINTENANCE OF CRUDE OIL STORAGE TANK NUMBER (1).
CONTRACTOR shall carry out repair works on Crude Oil Tank TK-01, 200 feet diameter x 48 feet high; capacity of 268000 barrels, Single Deck Floating Roof. Tank was designed and constructed/ erected in accordance with API 650. Vessel Classification: Class ‘A’, Material of construction: ASTM A-285 Gr. C.
The work includes: Detailed Engineering & Design, Procurement and delivery of materials, Repair of Tank damages which include Civil, Mechanical, Electrical and Instrumentation works (repair on Tank Shell/ Wind Girder/ Nozzles, Roof plates, Pontoon, Roof supporting legs & seals), Painting Works and Testing & Commissioning.
3- HOO Sirtica Transfer Pipeline Cathodic Protection System Upgrade HOO Tender No. FP (03/2020).
The Scope of Work in general is to the upgrade of the existing Cathodic Protection System of the Sertica Pipeline that includes, detailed engineering, procurement, installation and commissioning of all necessary equipment and materials as defined in the tender documents.
4- HOO Amal to Ras Lanuf 30” & 36” Transfer Pipelines Cathodic Protection Upgrade, HOO Tender No. FP (02/2020).
The Scope of Work in general is to upgrade the existing Cathodic Protection System of the 30″ & 36’ pipeline from Amal to Ras Lanuf with an approximate length of 300 Kilometers. The existing CP system was damaged and requires essential upgrade to order to mitigate pipeline external corrosion. The Scope of Works detailed engineering, procurement, installation and commissioning of all necessary equipment and materials as defined in the tender documents.
5- AKAKUS Quotation for Desludging of Surge Tank D-101B at NC-115 GOSP’A’.
The work in general consists of removal of the sludge content and disposal of waste to AOO designated area and manual cleaning of the Tank D-101B at NC-115 GOSP’A’.
6- AKAKUS INSTALLATION OF A BYPASS AROUND THE SURGE TANK D-201 & INSTALLATION OF ZALLAF PIPELINE TIE-IN AT NC-115 GOSP-B RFQ No. (QR-ENG-382-2020).
To avoid a prolonged production shutdown, AOO intends to install a piping bypass between the crude oil degassed pumps G-207A/B/C/D discharge and the booster pumps G-201A/B/C suction; and to install the minimum facilities required to facilitate the Zallaf pipeline tie-in with the inlet of the surge tank D-201 inlet without affecting GOSP ‘B’ production.
The work in general consists of engineering, supply, and installation of all required materials and equipment, piping, civil works, instrumentation and related works according to Company specifications.
7- SIRTE OIL COMPANY Replacement of Section of 36″ Crude Oil Pipeline at Km 0 to Km 23 (TP-208319-Z.).
The work in general is to install new 36” Ø crude oil pipe, buried, approx. 23 Km length which includes Engineering, Procurement, Installation and Commissioning (EPC) of all necessary equipment and materials as defined in the tender documents
8- AKAKUS Fire Fighting of Water Cooling Ring System Replacement at Stock Tanks D-102 A&B/ NC-115 (A).
The AKAKUS OIL OPERATIONS (AOO) intends to replace the fire fighting water cooling ring system of Stock Tank D-102A, D-102B at NC-115A at El Sharara Oil Field. Works is EPC Contract for the replacement of existing 3″ Ø riser (Vertical Line) and 2″ Ø water cooling rings piping system in accordance with the requirements of the tender documents . The work in general consist of engineering, supply, and installation of all required piping, flanges and fitting, complete with the required gaskets and bolts, welding, NDT/hydrotest, painting and coating.
9- AKAKUS El-Sharara NC-115 GOSP-A Surge Tank D-101B Bottom Replacement – SOW D-101A.
The objective of the project is to carry out the works which includes Engineering, Procurement and Construction (EPC) for the repair of Surge Tank # D101B, including of all required testing, cathodic protection, painting and coating, electrical and instrumentation, pre-commissioning, commissioning activities, all in compliance with the requirements of the tender documents
10- AKAKUS Installation of J26 Well Tie-in at NC186, El-Sharara RFQ No. (QR-ENG-397-2020).
The work in general consist of supply (except OFE), storage, collection from stores and transport to work location, installation of all piping, welding, NDT, painting of aboveground portion, hydrotesting, with all accessories like pipe supports, instruments, cables with accessories, cable termination junction boxes and tie-in to wellhead and manifold. Stringing ditching, welding, lowering wrapping, backfilling, leveling, hydrotesting and pre-commissioning of UG oil producing J-26 well pipeline, connection to the existing CP system, complete with anchor blocks all according to Company specifications.
11- AKAKUS Mechanical Modification of Production Separator C1001 A/B at Block 186 GOSP-A RFQ No. (QR-ENG-405-2020).
This project is based on EPC contract which includes Engineering, Procurement of equipment and materials, Installation and Construction including all required testing, pre-commissioning, commissioning and start-up activities. The work in general consists of detailed engineering, supply of all required materials, manpower, tools and equipment for the repair works/ modification of Production Separator C-1001 A/B.
12- WAHA NC98-Gialo III Field Development Project (Construction and Commissioning Works – CMEI).
The project consists of Oil Production Facilities and production gathering system which includes production well sites, multi-phase pumping station, water disposal well site, flowlines, trunklines, export pipelines, modification of existing stations, buildings & structures and all associated facilities. Construction and installation of the Central Processing Facilities (CPF), 29 well sites, 300km of pipelines, overhead power lines and distribution networks.
The project comprises of Construction and Commissioning of Civil, Mechanical, Electrical, Instrumentation and Telecommunication (CMEI). It consists of Oil Production Facilities and production gathering system which includes production well sites, multi-phase pumping station, water disposal well site, flowlines, trunklines, export pipelines, modification of existing stations, buildings & structures and all associated facilities. Construction and Installation of the Central Processing Facilities (CPF), 29 well sites, 300KM. of pipelines, overhead power lines and distribution networks.
13– Installation of 12″ Water Injection Trunkline at H-Field El-Sharara, Block 186 / RFQ (QR-ENG-402-2020).
EPC Contract for the complete Installation of new 12” Water Injection – Trunk Line between NC-186 GOSP-A produced water treatment plant (PWTP) area and the North H-field water injection facilities and laid the second portion of pipeline connecting North H-field and South H-field
14- El Sharara, NC-115 Stock Tank D-102A – Patch Repair.
The objective of this project is to repair the existing damaged tank shell and bottom plates by replacing/patching steel plates, welding & painting works.
15- El Sharara, NC-115 Tank D156-B– Tank Bottom blasting & Anodes replacement.
The scope of this tank preventive maintenance project is to perform bottom fiber glass removal and replacement, grit blasting & painting after completion of the bottom inspection and replacement of cathodic protection anodes.
16- El sharara Field Airport pavement repair Emergency Repair of Airport Concrete Pavement at El Sharara Airfield.
The repair works consist of cutting damaged concrete pavement, excavation, compaction and pouring bituminous concrete.
17- Installation of New Incinerator Facility for NC115 El Sharara Landfill Area (QR-ENG-423-2021)EPC Contract for Installation of Incinerator (Pyrotec G model) Facility at NC115 El Sharara.
The Incinerator Facility composed of Primary and Secondary Combustion Chambers inside of two (2) containers, including other related equipment such as Chimney, De-ash system, Bin Tipper, Ram Loader, Hydraulic Power Pack, Fuel and Water Tanks. The work includes installation of steel platforms & supports, steel stair, cage ladder, railings and other miscellaneous structural steel.
18- Replacement of Corroded 6” Pipeline Sections for Oil Wells H18, H26, H44, NH15-29 & WSW25 at NC115 El Sharara Construction / Replacement of corroded sections of the 6” flowlines for Oil Wells H18, H26, H44, NH15-29 & WSW25 at NC115 El Sharara Oil Field.
The work consists of excavation, backfilling, pipe cutting, welding, wrapping and hydrotesting.
19- Installation of NC115 GOSP-B 20kVA Un-interrupted Power Supply (UPS-201).
EPC Contract for Installation of new UPS system (OFE) at NC115 GOSP-B facilities including of all required testing and commissioning.
20- NC-115 Development Project.
Supply and Installation of 18” 6km Pipeline” EPC for Supply & Installation of 18″ dia. Pipeline approx. 6km including installation of Pig/Launcher Receiver.
21- Pilot Water Disposal System for Main Stations at Tibisti Field, Tender No. (07/2020).
The scope of work in general consist of design and engineering, supply and Installation of 3-½” dia. WI pipelines with approx. length of 6.6 Km from main station to well I-34 and well I-35 including modification of De-Salter/Buffer Tank and installation of pumps and associated pipeline at Tibisti Field.
22- Pilot Water Disposal System for Stations (3&6) at Amal Field, Tender No. (08/2020).
The work in general consist of supply and installation of 3-½” dia. WI pipelines with approx. length of 3.6 Km from station-6 to well N-45 including modification of De-Salter/Buffer Tank and installation of pumps and associated pipeline at Amal Field.
23- Ras Lanuf, Inspection & Repair PM EPC Contract of 500,000 US bbl Floating Roof Above Ground Storage Tank No.9.
The work in general consists of detailed engineering, supply of all required materials, manpower, tools and equipment for the reconstruction of damaged 500,000 bbl Floating Roof Crude Oil Storage Tank at Ras Lanuf Tank Farm. Repair of Tank damaged portion such as the center deck and pontoon, tank shell plates, tank bottom plates, structural steel, civil works such as tank concrete ring foundation replacement, pavement, miscellaneous platforms and pipe support foundations, piping, cathodic protection, instrumentation and painting.
24- Intelligent Pigging of 30” Gas & 12” Condensate Pipelines from Al-Asticklal (Al-Tahadi) to Km-91.5 (TP-213328AT).
The scope of work in general is to perform Intelligent Pigging of 30” Gas & 12” Condensate Pipelines consisting of cleaning the pipes with cleaning pig runs, gauge pig run, MFL tool runs, XYZ mapping, data evaluation and reporting. The work includes provision of Pig Launcher/receiver at both ends of the pipeline.
25- Intelligent Pigging of 16 Condensate Pipeline from Km 91.5 To Brega (TP-216301Z).
The scope of work in general is to perform Intelligent Pigging of 16” Condensate Pipeline consists of cleaning the pipes with cleaning pig runs, gauge pig run, MFL tool runs, XYZ mapping, data evaluation and reporting. The work includes provision of Pig Launcher/receiver at both ends of the pipeline.
26- Intelligent Pigging of 30 Gas Pipeline from A103 Field to SAHL Field (TP-218302SL).
The scope of work in general is to perform Intelligent Pigging of 30” Gas Pipeline consists of cleaning the pipes with cleaning pig runs, gauge pig run, MFL tool runs, XYZ mapping, data evaluation and reporting. The work includes provision of Pig Launcher/receiver at both ends of the pipeline.
27- Replacement of 68.5 Km. 16 “/ 24” Shipping Line from Nafoora GOSP106 to 103A Zueitina Company.
EPC for supply, installation and commissioning of new 12” Ø crude oil pipeline, buried, approximately 68.5 km long from Nafoora GOSP-6 to Zuetina 103A. The work includes all associated equipment like pig launcher & receiver, interconnecting pipework, block valve stations, laying of fiber optic cable, replacement of crude oil shipping pumps and crude oil metering system with new prover loop, upgrading of electrical and instrumentation system, supply and installation of one MVA Transformer and new Control Room, Cathodic protection system, fire detection and alarm system. AOS also to provide Camp Accommodation, Offices, Utilities and Logistic Facilities for the entire manpower and Client crews during implementation of the project.
28-EPC for New Sea Water Reverse Osmosis Package.
The work in general consist of replacement of existing Brackish Water Osmosis (BWRO) unit for a new one at Zawia Tank farm. Work includes design and engineering for supply replacement unit with a new equivalent to Sea Water Reverse Osmosis (SWRO), piping, civil, electrical, automation, instrumentation, plant lighting and commissioning.
29-EPC of El-Sharara Airport Firefighting Standalone System.
EPC Contract for El-Sharara Airport Firefighting Standalone System which consist of supply, installation and commissioning of Fire Water Tank, Jockey Pumps, Electric Driven Firewater Pump, Diesel Driven Firewater Pump, 4″ and 6″ Glassfibre Reinforced Piping main ring firewater network with hydrants, fire hoses and cabinets, and elevated Truck filling station complete with civil foundations, pump shelters/ sunshades and fencing, structural, fire detection system and electrical works.
30-Replacement of Bottom Plates for Stock Tank D-102A at NC-115 GOSP’A’/ (QR-ENG-447-2021).
The work consist of Tank Preventive Maintenance/ Repair of crude oil stock Tank D-102A at NC-115 El Sharara. The existing damaged tank annular & bottom plates will be repaired by replacing/patching steel plates,
welding & painting works.
31-El Sharara 18″ Trunkline – New 31 km Installation.
EPC for Supply and Installation of new 18″ dia. Trunk line, approximately 31 km, hauling, trenching works, welding, coat and wrap, testing and commissioning including installation of all associated equipment such as pig launcher & receiver, valve stations, instrumentation and cathodic protection system. Existing pipeline will be removed, cut into pieces and transport to Client storage yard.
32-Tender No (19/2021) Replacement of Wells Flow Lines at Amal Field.
The scope of work in general is supply and installation of 6” dia. Flow lines for 4 Nos. Oil wells at Amal field with a total length of 12.35 km. The installation & tie-in of flowlines consist of excavation, demolition, fabrication, erection, installation, welding, wrapping, painting, testing, pre-commissioning and commissioning. Work includes civil, instrumentation and cathodic protection.
33- Supply and Installation of New Chain Link Fence and Gates for Five (5) Wellheads
The work in general consist of Engineering, Procurement and Construction for the installation of new Chain Link Fence and Gates around the wellhead and OHTL Tower.
34- Intelligent Pig Survey of various Shipping Lines in AGOCO Oil Fields Tender No. O-95
This project will be done in partnership of GASTECH Engineering & Consulting France. The scope of work in general are MFL inspection of Oil & Gas shipping lines, Mapping of all shipping lines and Cleaning and gauging of shipping lines.
35- Tie-in of Water Line from Made River Pipeline at Awjilah to Nafoora Camp (MTC-25/2021)
The work consist of Construction, Procurement & Engineering of a 23Km. -8ӯ HDPE water line from Man-Made River tie-in point (AV/186+170) at Awjilah base to Nafoora camp. The objective of the project is to supply 700 m3 of potable water minimum daily demand of AGOCO Nafoora camp.
36- Reinstatement of Zenad Station to Produce of (15,000) BPD of GIR/Facha at Ghani Field
The objective of this project is the rehabilitation of Zenad Station oil production facilities consisting of installation & commissioning of Company’s supply equipment (OFE) for the replacement or refurbishment of surface facilities equipment which were damaged such as Crude Oil Storage Tanks ST-401 & ST-402, Degassing Boots V-404, V-405, Shipping Pumps, Recycle Pumps and other process Vessels. The work includes supply and installation of pipes, valves and fittings for the restoration of the Zenad process piping system, electrical, instrumentation and civil works.
37- Reinstatement of Farrud Water Injection with a Capacity of (25,000) BPD at Ghani Field
The Project is Turn Key Project- Engineering, Procurement and Construction (EPC) for restoration of Farrud Water Injection Station with a Capacity of (25,000) BPD of treated water in addition to the rehabilitation of power plant and Laboratory Building at Ghani Field.
38- Contract Area-E (El Feel Onshore Field) Tank (CP-T-PL-01A) Repair
The work in general consist of supplying design, drawings and field engineering services as may be required during construction, supply of labor, equipment and materials necessary to complete the repair works of existing Fixed Dome Roof Crude Oil Tank (CP-T-PL-01A) at GOSP plant in El Feel, with a capacity of 15900 m3 which include fabrication and installation/erection of steel bottom plates, repair the foundation and the cathodic protection system for the Tank bottom.
39- Construction of Protective Aircraft Shelter (PAS) at El-Sharara Airport
The work in general consist of Engineering, Procurement and Construction (EPC) of Protective Aircraft Shelter (PAS) at El-Sharara Airport in order to have a safe shelter for the Ambulance Aircraft.
40- NC-200 Erawin Field Development Phase 1 – Early Production Facilities, Subcontract ITB No.: JI-2047/03-001, CMEI and PIPELINE WORKS The project will be done in partnership with PETROFAC Engineering and Construction. The work in general consist of Construction and Commissioning of Civil, Mechanical, Electrical, Instrumentation and Telecommunication (CMEI) and Pipeline works
41- Rehabilitation of Berths 2A/B at Ras Lanuf Harbour, Ras Lanuf Complex – Libya
The work consist of Engineering, procurement and construction (EPC) for Rehabilitation of Berths 2A/B at Ras Lanuf Harbour based on Unit rates.
42- Mabruk Reinstatement Activities
Project comprises of Engineering, Procurement and Construction (EPC) for Contract ITB CFT №: CFT/MRP/470/2021/MBK Mabruk Rehabilitation Reinstatement Activities. CONTRACTOR shall perform technical and economic assessment for the existing facilities of new and old GOSP, Main generators, satellites, Node 1 in terms of control building, electricity cabinet, HV cables, flow lines, etc. Demolishing and removing all the damaged facilities. Installation of the satellites and oil wells (O.P.W) for 23 wells. Maintenance of the airstrip. Revamping the existing departure container. Construction of the Communication IT server and DATA center building. Renovation of Mabruk fire station building. Construction of the Warehouse and workshop, fencing, equipment recommissioning and commissioning works.
43- Maintenance and Installation for Zawia Meter Proving Systems
The project is to carry out the work for the maintenance and installation for Zawia Meter Proving System. Work implementation shall start with maintenance activities such as cleaning, flushing, removal, dismantling of calibration tank, piping supports, instrument calibration, testing etc. while final reinstatement and installation works will resume upon receipt of Company supplied (OFE) materials i.e. New Prover Sphere and Cylindrical Water Draw Tank (Calibration Can).
44- Tender (15/2022) EPC Contract (Engineering, Procurement and Construction) of New 12″ Low Pressure Gas Loop From Station 2 to Station 4 at Amal Field
The work consists of Engineering, Procurement and Construction (EPC) at Amal Field to replace The existing 16″ to 12″ gas line approximately 7.5 km distance, the existing buried 16″ Low Pressure Gas Loop From Station 2 To Station 4 at Amal Field